Solar-Plus-Battery Storage Project Commissioned in Bihar

  • 09 Jan 2026
  • 2 min read

Why in News?

Bihar has successfully commissioned the first phase of a large solar-plus-battery storage project in Kajra, Lakhisarai district.

Key Points

  • Implementing Agency: The project is being executed by Bihar State Power Generation Company Limited (BSPGCL), the state-owned power utility.
  • Project Capacity: The total project capacity is 301 MW solar power combined with 495 MWh battery storage.
    • This makes it one of the largest solar-plus-storage projects in eastern India.
  • Phase-I: The first phase consists of 185 MW solar capacity with 254 MWh Battery Energy Storage System (BESS).
  • Technology Used: The battery storage system uses Lithium Iron Phosphate (LiFePO₄) technology, known for higher thermal stability and safety.
  • BESS Function: The BESS enables storage of excess daytime solar power and supplies electricity during peak evening demand hours.
  • Grid Integration: Power from the project is evacuated through a 132 kV transmission system, ensuring seamless integration with the state power grid.
  • Second Phase: The remaining 116 MW solar and 241 MWh BESS will be commissioned in the next phase, expected by January 2027.
  • Strategic Importance: The project supports Bihar’s long-term goal of increasing the share of renewable energy and reducing dependence on conventional fossil-fuel-based power.
  • Environmental Significance: Solar-plus-storage projects help reduce carbon emissions, improve energy security, and promote sustainable power generation.