Gangajal Udvah Yojana | 07 Oct 2021

Why in News

  • On October 6, 2021, Chief Minister Nitish Kumar reviewed the works of 'Gangajal Udvah Yojana'.

Key Points

  • In the review meeting, Secretary, Water Resources Department, Sanjeev Hans said that the work of the original plan will be completed by March 2022 and the target has been set to start the water distribution work by June 2022.
  • A total distance of 150 km from Hathidah-Mohanje-Tetar-Abgilla Of the pipeline of about 118 km Pipe laying has been completed.
  • It is to be known that 'Gangajal Udvah Yojana' is an ambitious scheme of the Government of Bihar, through which pure drinking water will be provided to the people of Rajgir, Gaya, Bodh Gaya and Nawada.